Project process percentage
Project process percentage
85%
Project timeline
Project timeline
Equipping workshop 09/17/2019
Scheduled start date: 09/11/2019
Scheduled completion date: 11/11/2019
Actual start date: 09/17/2019
Actual completion date: 01/10/2020
Excavation, Implementation of construction pile, Lean Conceret 11/01/2019
Scheduled start date: 11/01/2019
Scheduled completion date: 01/08/2020
Actual start date: 11/01/2019
Actual completion date: 12/23/2019
skeleton 12/25/2019
Scheduled start date: 01/10/2020
Scheduled completion date: 12/05/2020
Actual start date: 12/24/2020
Actual completion date: 12/19/2020
block work 05/09/2020
Scheduled start date 05/09/2020
Scheduled completion date: 01/04/2021
Actual start date: 05/09/2020
Actual completion date: 11/26/2020
Scheduled completion date: 01/04/2021
Actual start date: 05/09/2020
Actual completion date: 11/26/2020
Facilities and mechanics of phase one 11/19/2020
Scheduled start date: 10/03/2020
Scheduled completion date: 06/23/2021
Actual start date: 11/19/2020
Actual completion date: 06/02/2021
Scheduled completion date: 06/23/2021
Actual start date: 11/19/2020
Actual completion date: 06/02/2021
Phase one electricity 11/19/2020
Scheduled start date: 10/26/2020
Scheduled completion date: 06/15/2021
Actual start date: 11/19/2020
Actual completion date: 05/08/2021
Scheduled completion date: 06/15/2021
Actual start date: 11/19/2020
Actual completion date: 05/08/2021
Implementation of the body cover 04/11/2021
Scheduled start date: 04/04/2021
Scheduled completion date: 02/21/2022
Scheduled completion date: 02/21/2022
Implementation of floor covering 01/30/2021
Scheduled start date: 01/04/2021
Scheduled completion date: 12/08/2021
Scheduled completion date: 12/08/2021
Building facades 12/09/2020
Scheduled start date: 12/12/2020
Scheduled completion date: 04/03/2022
Scheduled completion date: 04/03/2022
The facilities of the second phase 07/16/2021
Scheduled start date: 07/23/2021
Scheduled completion date: 08/26/2021
Scheduled completion date: 08/26/2021
Phase two electricity 10/20/2021
Scheduled start date: 10/26/2021
Scheduled completion date: 08/25/2022
Scheduled completion date: 08/25/2022
Elevators 12/15/2020
Scheduled start date: 12/10/2020
Scheduled completion date: 08/16/2022
Scheduled completion date: 08/16/2022
09/22/2022 Delivery of the unit to residents
Scheduled start date: 09/22/2022
Scheduled completion date: 09/22/2022
Scheduled completion date: 09/22/2022